Update from Widnes

Stobart Rail continue to work at Widnes on the new Bio-Energy CHP Plant.

Testing of the Mersey Bio-Energy CHP plant at Widnes will start in mid-October with 500 tonnes of waste wood supplied for the testing period, in advance of commissioning in December 2016. The start of the commercial operation will be in April 2017.

The Widnes dryer is now installed and the heat off-take pipework is due to start in a couple of weeks. The conveyor system installation is planned for 19 September with the whole operation ready for hot/cold commissioning in December.

 